DIG Report End July 2021

DIG AGM

The DIG AGM was held during July. The main points were that the accounts for 2020/2021 were audited and signed off by Bob Hawkins, the bank accounts is now closed and funds transferred to HVRA. In addition, the new constitution was approved and officers agreed to continue.

Drainage Issues

Trees Rd suffered from a heavy day’s rain with the road grills overflowing and a large amount of puddling at the foot. The Trees Rd team cleared the grills a day or two after.

We reviewed this with Jonathan Roberts the drainage engineer from Bucks CC. He will consider possible additional work, such as joining the grill soakaways to the road drains pipeage. Also he will look at the road surface & edging blocks at the foot of Trees Rd. This will not be priority work.

The DIG team also met with Jonathan to look at the drainage issue that we have at the corner of Boss Lane by the Hopkins field gate and which can lead to flooding of Boss Lane. There is an issue of drainage pipe sizing here plus some other problems. We have not been successful in making progress. Jonathan agreed to conduct some research  into historical survey data and also to look at possible solutions to our problem.

Paul Woodford