- Harrow Area Flooding
We are slowly progressing towards assembling a response to Bucks Council regarding the Harrow area flooding. Paulw has conducted a visual check on the area up to the top of Warrendene Rd and Matt Hopkins is part way through checking drainage at Hatches, Bryants Bottom Rd and Hampden Rd.
We hope to be able to write to Bucks Council by the end of June.
- Thames Water
Pumping out at the Surgery has continued through this month and tankering from Boss Ln. The latter is becoming increasingly unpopular with the residents of Boss Ln because of noise and access problems.
The DIG met with a small team from TW this month. Results from meeting:
- We now have a permanent contact for the DIG in Maisie Banks, Custoner Liaison engineer.
- Mark Dolby (Snr engineer) is in the process of putting forward suggestions for hydro-braking for Hughenden Valley. This has to be data modelled for the whole valley and will include the Naphill & HV sewer junction problem. No timescale available on this.
- TW looking at reducing the frequency of overtankering with the weather improvements
- There will be a cleanup done in Boss Ln and the field below the pumping station when tankering /field leakages finished.
- Chiltern Society
Paul meeting with James Donald of Revive the Wye group 17th June.
Paul Woodford